DRAB Delivers Engineering Stability for Future Mobility

Tieback Retaining Wall Design in Amman, Delivering a More Economical Solution

Geotechnical Engineering | Retaining Wall Design

October 2026

DRAB Engineering Consultants has successfully completed the detailed design of a permanent tieback retaining wall for a commercial EV charging station development in Amman. The design replaced a conventional retaining wall, which would have consumed valuable land and budget, with a lean, rock-anchored solution that has been approved by the Jordan Engineers Association (JEA) and the Greater Amman Municipality (GAM).

The project involved an open excavation of approximately 21 m in limestone bedrock, extending around 100 m along the site.

A Costly Requirement on Stable Ground

The bedrock at the site was competent and self-standing. On its own, it would have required only rock stabilization works to protect against falling debris and long-term weathering.

However, project requirements called for a full-height permanent retaining wall along the entire excavation. A conventional wall of this height would need a foundation at least 8–12 m wide, taking a significant strip of land the owner planned to use for business space, along with large quantities of concrete and reinforcing steel.

The client approached DRAB to find a more economical and optimized alternative.

Engineering a Solution That Works With the Rock

Following a ground investigation carried out under DRAB’s direct supervision, the rock mass was characterized using the Geological Strength Index (GSI) methodology to establish reliable design parameters.

DRAB designed a tieback retaining wall supported by nine rows of fully grouted tiebacks, 4–9 m long and installed at 20° into the bedrock. The tiebacks transfer lateral loads directly into the rock mass, significantly reducing the bending moments and forces the wall itself must resist.

The design was carried out with reference to FHWA GEC No. 4, BS 8002, Eurocode 7 and ACI 318-19, with structural analysis performed in ETABS.

Measurable Value for the Client

The tieback design reduced the footing width to just 2.5 m, compared with the 8–12 m required for a conventional wall. This returned a large strip along the full length of the wall to the owner for business use.

The wall itself is a slim 200 mm section, locally thickened at the anchor heads, resulting in significantly lower concrete and steel quantities. Design checks confirmed a maximum settlement of only 3 mm, with bearing pressures well within the allowable capacity.

Delivering Value Through Engineering Expertise

This project reflects DRAB’s approach to geotechnical design: understanding the ground well enough to let it share the load. Rather than building bigger, the right solution came from working with the site’s natural conditions.

By combining site investigation, rock mass assessment, and integrated geotechnical and structural design, DRAB continues to help clients reduce costs, recover usable space, and build with confidence.

Design smart, build better.

Recent News

DRAB Delivers Engineering Stability for Future Mobility

DRAB Completes the Structural Assessment of Everest Building

DRAB’s Shoring Design Advances at Karak Health Center Project